1

THE RESIDENTIAL COMPLEX CRYSTAL AVENUE CONSTRUCTION: REPORT AS OF THE BEGINNING OF

09.03.2023

Herein it is being told about the current state of affairs at the construction site of the  residential complex "Crystal Avenue" in Petropavlivska Borshchahivka .

In the second phase (11-A, Oksamytova St.) hall decoration works, works on connection of power supply networks and territory landscaping are ongoing. Waterproofing works have also started.

In the fourth phase (1, Kryshtaleva St.) the ventilated facade installation (75% complete) and the wet facade installation (65% complete) are ongoing. The gasification of the house (40% ready) and the fire equipment installation (60% ready) have started. Workers are preparing to start finishing works in the near future.

To evaluate the construction with your own eyes or to contact our managers, please call +380960230310.