Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
In the second section, preparations for commissioning are underway.
In the third section, facade work (80% complete), installation of heating and water supply systems, floor screeding (30% complete), installation of railings (30% complete), installation of technical doors and installation of fire protection systems (80% complete) are ongoing. Electrical work has begun, as well as preparations for the installation of apartment doors and finishing work.
In the fourth section, monolithic work continues on floors 5-6. Preparations for bricklaying walls and partitions have begun.
In the fifth section, monolithic work continues on floors 4-5.
In the underground parking lot, works continue on landscaping between sections 1 and 2 and the installation of fire protection systems in sections 1-3.
You can make an appointment for a viewing or find out all the information about the Shchaslyvyi Grand residential complex by calling: +38 067 572 27 60.
For information on the upcoming lease of commercial space in the shopping center “Shchaslyvyi Mall”, please call: +38 095 210 98 64.