Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
In the second section, preparations are underway to sign the main notarized contracts, and the process of connecting to the gas and electricity grids is in progress.
In the third section, finishing work is underway (95% complete), along with landscaping around the building, installation of a playground, planting of greenery, and preparations for commissioning.
In the fourth section, window installation is underway (85% complete), as is the installation of water supply and sewer systems (50% complete), facade work (70% complete), roofing work, and preparation for plastering and screeding.
In the fifth section, concrete work is underway on the floors 10-12, including the construction of walls and partitions (30% complete), and preparations for window installation.
In the sixth section, concrete work is underway on the basement level.
In the seventh section, the excavation work has been completed. Preparations for the concrete work are underway.
In the underground parking lot, electrical work, road marking, and final finishing touches for Phase 1 have been completed. Installation of fire protection systems in Section 5 is underway, along with preparations for commissioning.