Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
The fourth phase (1 Kryshtaleva str.): the process of connecting electricity supply on a permanent basis is compete.
In the fifth phase (1-B Kryshtaleva str.), finishing works are continuing in the lobby, the facade of the first floor is being fitted out (95% complete), irrigation systems are being installed, landscaping works are underway, plants are being planted, all building systems are being tested, the building is being connected to water and electricity supply networks, preparations are being made to commission the building, and preparations are being made to transfer the apartments to investors.
In the last part of the underground parking lot, landscaping works, flooring and installation of the fire safety system are underway.