Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
The fourth phase (1 Kryshtaleva str.): the process of connecting gas and electricity supply on a permanent basis is underway. The house has been commissioned.
In the fifth phase (1-B Kryshtaleva str.), facade works(98% complete), finishing of the mixed-use building and staircases (65% complete), installation of technical doors (95% complete), installation of window and door structures on the 1-2 floors (60% complete), internal and electrical works (80% complete), installation of boilers and radiators (20% complete), and landscaping works are underway. Commissioning works have begun.
In the last part of the underground parking lot, landscaping works are underway, preparations are ongoing for flooring and installation of a fire safety system.