1

CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (NOVEMBER 2024)

30.11.2024

Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.

In the fourth phase (1, Kryshtaleva St.), lawn laying and tree planting have been completed. Preparations for commissioning are underway.

In the fifth phase (1 – B, Kryshtaleva St.), facade works are in progress (85% complete), plastering works (95% complete), screed installation (90% complete), gas supply installation (60% complete), and fire door installation. Interior finishing and electrical installation works have begun. Preparations for the installation of elevators have begun.

In the last part of the underground parking lot, work on the insulation and waterproofing of the parking lot has begun.

You can find out details about the construction, terms of purchase of housing or promotional offers by calling: +380960230310.